Standard custom builds: 25–45 days from design approval. We stock core materials so we don't lose weeks waiting for raw materials.
We can expedite, but we won't cut corners. Tell us the deadline, we'll tell you what's possible. We won't promise a 15-day transformer — that's how you get a transformer that fails.
Yes. Every unit undergoes routine tests before leaving. FAT on-site or video recording available. Test reports ship with every unit — your specific equipment's actual data, not a 'typical' report.
Routine: ratio, winding resistance, impedance, load loss, no-load loss, dielectric, induced overvoltage. Type (on request): temperature rise, lightning impulse. Special (on request): noise, partial discharge, zero-sequence impedance. KEMA/CEESI short-circuit testing available.